How do I Program a Second SwitchBox 56 to run Electrodes 57 to 112

Set a second SwitchBox56 to start at 57 so you can run two SwitchBox56's for a total of 112 Electrodes

Plug in only 1 Switch Box 56 at a time to the SuperSting

Turn the SuperSting on and follow these steps from the Main Menu

  1. Test Menu (3)
  2. Program Address (5)
  3. Address = 57
  4. Serial Number = 1
  5. Press F3
  6. Press Period (.) to confirm
  7. Set these values next
  8. Test Menu (3)
  9. Program Address (5)
  10. Address=85
  11. Serial Number =2
  12. Press F3
  13. Press Period (.) to confirm
  14. Label with white tape and a marker that this Switch Box handles Electrodes 57 to 112
  15. To confirm that you have programmed 57 to 112, run the Relay Test from 57 to 112 as described here. 
  16. Finally, label with white tape and a marker that the first Switch Box handles Electrodes 1 to 56 and connect both Switch Box 56's at the same time and run the Relay Test from 1 to 112